The Sequel Seattle is a mixed-use building located in the historic Pike Place Market District that offers both residential living and hotel apartments. The building is also home to many restaurants, retailers, and community spaces, including a rooftop bar with an exterior terrace that provides scenic views of the city and Puget Sound. Standing at 11 stories tall at the intersection of First Avenue and Stewart Street in the heart of downtown Seattle, the building boasts a unique unitized curtain wall façade. The eye-catching design acts as a visual gateway between downtown neighborhoods.

Touchstone Corporation enlisted Olson Kundig and our team to design and support the delivery of the building’s enclosure system. As the building enclosure consultant, we focused on ensuring the design met the design team’s expectations while still being constructable. We assisted the team in incorporating both a unitized curtain wall and a unitized wall panel system for the building enclosure.

As the project progressed, our team confronted the challenge of the unique unitized curtain wall design. The irregular interfaces in this design presented numerous opportunities for air and water leakage that could compromise the system. Since this design element was an important visual component of the project, our team sought to provide a design solution that would support this system. Working alongside Olson Kundig, our team participated in several rounds of design review and offered alternatives that would ensure the building’s design did not impact its airtightness rating. One of the strategies that was implemented included triple-glazed energy efficient windows.

Our team was also present during construction to provide field review and complete both water testing and whole-building air leakage testing. During the air leakage testing, our team worked collaboratively with the contractor to identify air leakage locations and to address air leakage issues while the test was in progress.

Through a concerted effort from the project team, the Sequel Seattle was completed as originally envisaged and opened its doors in 2018.

Date:

March 26, 2020

Client:

Touchstone Corporation

Architect:

Olson Kundig

Our Role:

Building Enclosure Consultant

Key Services

Concept Review
Construction Document Review
Field Review
Testing

Before material and systems selections are finalized, our clients benefit from a review of the building enclosure design strategies at a conceptual level. This review provides an opportunity to reflect upon the performance expectations and fundamental building science strategies behind the selection of appropriate solutions. Experience shows that changes made at the conceptual stage of building enclosure design have far greater cost-to-benefit impact than those made during late design or construction. A typical concept review considers the following:

  • Environmental loads
  • Energy performance targets and compliance options
  • Life cycle expectations
  • Constructability, sequencing, and complexity of detailing
  • Structural support
  • Risk analysis

Michael Kramer | LEED AP

Principal, Senior Building Science Specialist
View Bio

David W. Fox | PE

Associate, Senior Project Manager
View Bio

Kinects Tower

Kinects Tower is a 41-story, mixed-use tower that is designed to accommodate the lifestyles of those who live and work in downtown Seattle.