The site of the Comox Municipal Works Yard was originally developed as a municipal dump, taking all of the town’s refuse from 1949 to 1976 and then a reduced selection of items until 2005. In 1976, the Town of Comox began developing the site and added new structures over the years. By 2012, a total of 6 buildings had been built for municipal operations, including buildings for the Public Works and Parks Departments, and storage for fuel, hazardous materials, seasonal materials, and general items.

In preparation for the town’s plan to upgrade and improve their facilities site, RDH was retained in 2012 to complete an initial condition assessment and capital needs study of the existing buildings. Our assessment addressed current safety and space requirements. In addition, it included conceptual planning, siting, and budgeting for the upgrades as well as phasing to allow ongoing municipal operations during the construction phase. Based on our assessment, the town decided to rebuild several of the buildings on the same site and bring them up to date with improved energy efficiency, disaster response capabilities, and future growth capabilities.

We led the project on behalf of the town throughout the duration of the rebuilding process. As the project manager, we put together the design team and managed it as well as the building permit process, contractor selection, tendering process, construction overview budget, construction and deficiency work, and warranty work.

Some special features of the project included stormwater infiltration to reduce the municipal storm water collection load and voluntary compliance with the energy requirements of ASHRAE Standard 90.1. Our team provided expertise for compliance with the energy requirements. We also ensured the buildings were designed to meet the town’s request to provide accommodations for increased female staffing in construction roles.

This project was completed on time and significantly under budget. The phasing plan that our team developed allowed the Public Works and Parks Departments to maintain their operations throughout the construction process.

Date:

May 2, 2019

Client

Town of Comox

Architect

Vic Davies Architecture

General Contractor

AFC Construction

Key Services

Building Enclosure Condition Assessments and Investigations
Renewal and Rehabilitation

A building enclosure condition assessment (BECA) and investigation may be required when an enclosure is suspected of having a problem, such as a leak. A BECA report describes either the current condition of the overall enclosure or specific components, such as windows or a balcony, and aims to identify problems or potential problems. If we detect failures, we will recommend the next steps that may lead to repairs or a renewal.

Our team will review the original building drawings, carry out an owner survey, and then spend time onsite visually reviewing various components of the building enclosure. In addition, we will make exploratory openings to assess the condition of hidden components. Our team may use a range of testing and special analysis techniques, such as thermography. We provide a written report of our findings and recommendations and present them at meetings with the owner group.

Harvey Goodman | P.Eng.

Building Science Specialist
View Bio

Lord Shaughnessy

The Lord Shaughnessy is a unique building in Victoria. Constructed in the 1980s, the 4-story residential building is not only a concrete rather than wood structure, but its angular geometry and thoughtful composition of materials, textures, and colors lend it a striking appearance.

Read More
Lord Harley

Lord Harley

The Lord Harley Apartments showcase how a comprehensive renewal project can breathe new life into an older existing building.

Read More
RDH Building Science